Compressive Strength Test of Concrete Cubes

Cube Testing of Concrete is a standard method used to determine the compressive strength of hardened concrete. It’s one of the most widely used tests in civil engineering for quality control on construction sites.


Purpose of Cube Test

To ensure that the concrete mix used in construction meets the required compressive strength as per the design specifications (e.g., M20, M25, M30 grade, etc.).


📦 Cube Test Procedure

1. Sampling of Concrete

  • Fresh concrete is collected during casting.
  • Sample is taken as per IS 1199:1959.

2. Mould Size

  • Standard cube size: 150 mm × 150 mm × 150 mm
    • For concrete with aggregate > 20 mm, standard cube is used.
    • For aggregate ≤ 20 mm, 100 mm cube may be used.

3. Casting of Cubes

  • Fill the cube mould in 3 layers, each approximately 50 mm thick.
  • Tamp each layer 25 times using a standard tamping rod.
  • Finish the surface smoothly with a trowel.

4. Curing

  • Keep the moulded cubes in a moist environment for 24 hours.
  • After demoulding, cure the cubes in a water tank for 7, 14, and 28 days.

5. Testing (as per IS 516:1959)

  • After the curing period, the cube is tested in a compression testing machine (CTM).
  • Load is applied gradually at the rate of 140 kg/cm² per minute until failure.

📏 Calculation of Compressive Strength

Compressive Strength (N/mm²)=Load at failure (N)Area of cube face (mm²)\text{Compressive Strength (N/mm²)} = \frac{\text{Load at failure (N)}}{\text{Area of cube face (mm²)}}

  • For a 150 mm cube:

    Area=150×150=22500 mm2\text{Area} = 150 × 150 = 22500 \text{ mm}^2


📅 Test Age

  • Common testing days: 7 days and 28 days
  • 28-day strength is considered the characteristic strength.

📋 Acceptance Criteria (As per IS 456:2000)

  • Average strength of 3 cubes ≥ Target strength
  • No individual cube should be less than 85% of the grade strength

📘 Example

For M25 grade concrete:

  • Target strength = 25 N/mm²
  • 3 cubes tested at 28 days:
    • Cube 1: 26 N/mm²
    • Cube 2: 25.5 N/mm²
    • Cube 3: 24.2 N/mm²
    • Average = 25.23 N/mm² → Acceptable (above target)
    • Minimum = 24.2 → > 85% of 25 = 21.25, so still acceptable

🔧 Precautions

  • Proper mixing and compaction
  • Moulds should be oiled and properly aligned
  • Curing should be adequate
  • Test machine must be calibrated.

Cube Test Checklist for Site Engineers / Technicians

S. No. Activity Check/Action Remarks
1 Concrete Mix Grade Confirm mix design (e.g., M20, M25, etc.)
2 Cube Moulds Condition Cleaned, oiled, and free from deformation
3 Mould Size 150 mm × 150 mm × 150 mm
4 Sampling of Fresh Concrete Taken as per IS 1199
5 Filling of Cube Mould In 3 equal layers
6 Compaction 25 blows/layer using standard tamping rod
7 Surface Finishing Trowel finish, flush with mould top
8 Curing Before Demoulding Covered with moist hessian or plastic sheet For 24 hours
9 Demoulding Time After 24 ± 2 hours
10 Cube Identification Marking Date, cube number, mix grade
11 Water Curing Duration 7, 14, 28 days
12 CTM Calibration Check Ensure machine is calibrated
13 Test Age Record curing age on test date
14 Testing Procedure Load applied uniformly until failure As per IS 516
15 Record Peak Load Load in kN or N
16 Calculate Compressive Strength Load ÷ Area of cube face
17 Evaluate Result Check against design mix & IS 456

📄 Sample Cube Test Report Format

CONCRETE CUBE TEST REPORT
Project Name: XYZ Construction
Location: __________________
Client: ____________________
Tested By: ___________________
Lab/Agency: __________________
Report No.: __________________
Date: //____

S. No. Cube ID Date of Casting Grade Size (mm) Test Age (Days) Date of Testing Load (kN) Strength (N/mm²) Result
1 C-01 10/06/2025 M25 150×150×150 7 17/06/2025 470 20.89 Pass
2 C-02 10/06/2025 M25 150×150×150 28 08/07/2025 600 26.67 Pass

Compressive Strength = Load (N) / Area (mm²)
Area = 150 × 150 = 22,500 mm²

Remarks: Cubes meet required strength criteria as per IS 456:2000.

Tested By: _____________
Approved By: _____________

Leave a Reply

Your email address will not be published. Required fields are marked *